Project Name         Date  
 
  JNK-YNCC NCC#2 Revamp Material Supply
2019. 07. ~ 2020. 01.  
  National Museum of Contemporary Art, Korea Gwacheon Hall 5,6 Show Room
Old Facilities Improvement Work
2019. 07. ~ 2019. 10.  
  JNK-HDO 2020 Revamp (RDS E18-52 ,53 Heater) Instrumentation Work 2019. 06. ~ 2020. 05.  
  Gyeonggi Provincial Office of Education - Songnae High School
air conditioning and heating LED lighting Improvement Electric Construction
2019. 01. ~ 2019. 04.  
  Gyeonggi Provincial Office of Education - Neulpureun Middle School
LED Lighting Replacement Work
2019. 01.  
  Gyeonggi Provincial Office of Education - Gwangju High School
Teacher Area Washroom Improvement Electric Construction
2018. 12. ~ 2019. 02  
  JNK-HTC BTX Revamping Project Instrumentation Work 2019. 04. ~ 2019. 05.  
  JNK-HDO MX CCR Revamping Project Instrumentation Work 2018. 12. ~ 2019. 06.  
  JNK-HDO Coker Heater-2(OLD COKER RVAMP) Instrumentation Work 2018. 05. ~ 2018. 10.  
  JNK-BAPCO-5CDU Project Instrumentation Work 2018. 02. ~ 2018. 11.  
  JNK-HDO Revamping_#1DCU Instrumentation Work 2018. 05. ~ 2018. 10.  
  PCK-HDO Revamp HS-19-03,04 Instrumentation Work 2018. 05. ~ 2018. 10.  
  PCK-Soil-DY HC2 Project_Refomer 2018. 05. ~ 2018. 09.  
  JNK-Hyosung-DH-1 Improvement Project-D.A 2017. 06. ~ 2017. 11.  
  JNK-HDO VC Revamping & Coker Heater Instrumentation Work 2018. 05. ~ 2018. 10.  
  PCK-K0504 HDO SDA Project Instrumentation Work 2018. 02. ~ 2018. 05.  
  JNK-KPIC One Project - Hook UP Material Delivery 2017. 03. ~ 2017. 06.  
  PCK-OCI-BTX DBNK Project Instrumentation Work 2016. 11. ~ 2016. 11.  
  JNK-HDC MX Project Heater Instrumentation Work 2016. 04. ~ 2016. 10.  
  Yeongheung Power Plant Soot Blower (No.2, 3) Instrumentation Work 2015. 11. ~ 2015. 12.  
  Hadong Power Plant Soot Blower (No.2, 3) Instrumentation Work 2015. 04. ~ 2015. 05.  
  Icheon Police Station Zeungpo Police Substation Electrical Work 2015. 08. ~ 2015. 12.  
  PCK-TOYO-K ECU&PE-PP Project Panel Delivery 2015. 03. ~ 2016. 02.  
  PCK-RA/SN PH-III Project Panel Delivery & Instrumentation Work 2015. 01. ~ 2016. 01.  
 

JNK-S-OIL ARO.2 CCR ID FAN Revamp Project Electrical & Instrumentation Work

2015. 03. ~ 2015. 08.